Summary: Resource allocation of 1.000 people

At first, information was scattered across the workplace

In an organization of a 1.000 people, resource allocation is carried out on many different levels. This guide is an overview of up-to-date resource allocation information of a relatively big organization, as well as the benefits that can be gained from it in an organizational level.

The organization’s own personnel and invoiceable work

Our example organization works mainly on projects that are invoiced by the hour. The green line in the chart indicates the capacity of the organization’s personnel. It shows the maximum number of working hours that the personnel can get done within a typical work day.

The blue area, respectively, indicates the booking situation (resourcing) in invoiceable projects. The chart shows the invoicing rate of our example organization as an area in relation to the capacity. 

Graafi 1_1000 hlö resursointi

By setting an average targeted invoicing rate for the people, we can also see a forecast in relation to the set target. The yellow line indicates the targeted invoicing rate, which the blue area of invoiceable resources tries to achieve with the help of organizational actions.

Graafi 2_1000 hlö resursointi

The forecast naturally depends on the length of the projects, as well as their predictability. A 4-12-month forecast is relatively common for project activity.

Our example organization is striving to gain the set targeted invoicing rate by project sales, hourly invoicing and successful resourcing. Our example organization utilizes its invoicing rate for living, to manage its payroll, pay invoices and maintain its ability to function.

An organization that works on projects invoiced by the hour should breathe the information provided by these resource charts, such as actual resource information, when managing its resources, production and sales on a regular basis.

From money to working days

Besides invoiceable projects, an organization of 1.000 people also develops and educates itself, prepares products or services and administers. The darker area in the chart indicates the resourcing of the personnel in internal or non-invoiceable projects.

Graafi3_1000 hlö resursointi

The joint area of invoiceable and non-invoiceable resources makes up the forecast of the organization’s utilization rate. It reveals the workload of their personnel in relation to their capacity.

As the invoicing rate approaches the utilization rate, the personnel only work on invoiceable work. This is a great moment to stop and ask, whether education and development are at an adequate level in the organization. 

Enough work, enough play

Enough invoiceable and internal work are necessary for our example organization to function and develop. Enough vacation and absence days are necessary for the wellbeing of the personnel. The resource management of absence days is also important to our example organization because of the availability forecast and invoicing potential. 

The green resourcing area in the chart indicates absence days.

Graafi 4_1000 hlö resursointi

The joint area of the resourcing of different kinds of project work and absence days makes up the forecast of the resourcing rate of the organization’s personnel. The chart indicates the high level of commitment of the people to the organization’s actions. 

Too great a difference between the capacity and the resourcing rate results in cost inefficiency. The organization may also be incapable of predicting resource allocation or is not willing to do it. 

Name-calling isn’t ugly

It’s not always possible to identify all roles when allocating project resources. The pink area indicates the unnamed allocations in the organization’s project database.

Graafi 5_1000 hlö resursointi

Now the joint area of the chart indicates the forecast of the organization’s forecasted resourcing rate. Our organization uses it to predict needs over a longer time span and to communicate acute deficiencies in projects.  

The same laws apply to the forecasted resourcing rate and the resourcing rate. Still, the target is set deliberately, offering backup for surprises and protecting the personnel from burn-out.

The forecasted resourcing rate may rise remarkably in the future, exceeding the capacity. That’s when there are more project needs than human resources in the organization. These needs can be met by recruiting so called future talents, adding externals or shifting the focus from non-invoiceable projects towards invoiceable projects.

Nothing is as uncertain as uncertainty

The organization strives to constantly sell new projects, whereas the so-called prospect projects keep confusing the project allocation situation with certain probabilities.

In the chart below, the gray area indicates resources allocated to persons and unnamed roles (including the organization’s own personnel and externals) in uncertain projects. These uncertain allocations are also scaled by the probability of project acquisition. Additional statistical information can be drawn from such a large mass of projects and used to predict future capacity.

 Graafi 6_1000 hlö resursointi

Resource allocation is not simple

The resource allocation of a project portfolio of a large organization is far from easy and there are a lot of questions. It’s essential to an organization to be able to keep their resource allocation information up-to-date, define targets for their project activity and to manage their actions with their resourcing situation and targets in mind. A successful throughput of projects is fundamental to all this.

This article is a brief summary to this theme. Download the Resource allocation of 1.000 people -guide from here.